The project includes expansion (12,000 - 15,000 SF) of the State University Building into the courtyard between the existing State University Building and Haggerty Administration Building to include the creation of additional campus conference space, impromptu student presentation/ gathering space, and a more grand entrance to the campus bookstore.
The project during construction and later during operation will be the most environmentally friendly project on the SUNY New Platz campus, complete with low/zero impact mechanical and electrical support systems as well as sustainable finishes throughout.
RESPONSIBILITY:
Jois Construction Management was responsible for developing the detailed cost-loaded Baseline construction schedule for the project, incorporating long lead procurement items, interim milestones, and phasing requirements for the project. On a monthly basis, the approved Baseline schedule was updated with schedule and cost information, and the critical path was analyzed to determine the impact on project completion and critical issues impacting the project. As necessary, any changes in the work plan were incorporated into the schedule on an ongoing basis.
Jois Construction Management was also responsible for delay analysis which included a review of change orders and evaluating their impact on scheduled completion date.