NJ Turnpike - CM & Inspection Services Mainline Interchange 6 to 9 Widening Program
Owner: NJ Turnpike Authority
Project Cost: $ Various
The Interchange 6 to 9 Widening Program includes road widening and associated interchange improvements for approximately 35 miles stretch of NJ Turnpike from Milepost #48 to Milepost #83. Upon completion of the program, the Turnpike will have 6 lanes in each direction from Interchange 6 to 9, with three lanes in each direction dedicated to “cars only” traffic. The Program includes Road Widening, Interchange Improvements, Toll Plaza Construction, Utility Relocations, Landscaping, and Freshwater Wetlands Mitigation. The Program has been divided into 8 sections in addition to several utility relocation and improvement contracts; approximately 30 construction Contracts will be awarded to execute the program.
RESPONSIBILITY:
Jois Construction Management provided Scheduling services which included the development and maintenance of the Program Schedule, forecasting staffing resource and funding requirements, reporting actual status, reviewing/ analyzing Contractors' resource/cost-loaded schedules, integrating Contractors' schedules into the Program Schedule, and incorporating findings into Progress Report.
Jois Construction Management prepared Change Order Estimates including scope preparation of the change, analysis for entitlement, take-off quantities from contract drawings and change order drawings, pricing, and preparing the Engineer’s estimate in the same format as the contractor’s proposal.